UNCG Campus Weekly

Campus Weekly is published each Wednesday when classes are in session. In the summer, it is published biweekly.

Project Cut-Off Dates

The project cut-off dates for fiscal year 2009-2010 have been established. “In keeping with state and university policy, we will not pre-bill for work in progress or incomplete projects,” says Cynthia Barnes, assistant director of renovations. Funding for projects utilizing 2009-2010 funds must be received by Jan. 29 for projects involving renovations requiring design services and the N. C. State Construction Office approvals and April 15 for simple projects involving only painting or simple office relocations. All work must be completed by June 4.

Full information can be viewed in a memo posted online.

Those with questions may call 4-4150.